Monday, December 31
No visit this week
We didn't visit the house this week since there wasn't anyone in the sales office to let us in. Instead we ordered some sample paint colors and picked up a few samples of some tile for the kitchen floor. Apparently Sundays are not good days to look for tile because most of the stores are closed! While we are not getting the premium travertine I love (it's just not practical with kids and dogs), we did find some nice porcelains. A couple of weeks ago, we got a tile saw too. It will cut a 18" diagonal, but not we might do an offset pattern like the premium travertine was laid out.
Sunday, December 23
Matt visits the house
This week Dave's brother was in town so he saw the house for the first time. It didn't look any different than last time. We still don't have a master tub or toilets in many of the bathrooms. They did repaint the interior and some of the exterior though because we saw wet paint signs.
Today was a hard day though. After seeing the house, Dave and I went and bought our refrigerator and washer and dryer. It was a lot of money -- too much money. I feel robbed!
Today was a hard day though. After seeing the house, Dave and I went and bought our refrigerator and washer and dryer. It was a lot of money -- too much money. I feel robbed!
Friday, December 21
Countdown begins
We are less than 30 days out from the close! Right now I am working on securing a mortgage rate. Next, we need to order a fridge and pick paint colors.
We did buy a tile saw and have selected a couple of tiles for the kitchen. However we haven't finalized it yet. We found out the tile we love (see pictures we posted), is a PREMIUM travertine that costs $10/sqft. That's as much as hardwood so we decided we would either consider hardwood or do a porcelain. With a dog and a toddler, it's probably smart to go with the porcelain.
We did buy a tile saw and have selected a couple of tiles for the kitchen. However we haven't finalized it yet. We found out the tile we love (see pictures we posted), is a PREMIUM travertine that costs $10/sqft. That's as much as hardwood so we decided we would either consider hardwood or do a porcelain. With a dog and a toddler, it's probably smart to go with the porcelain.
Monday, December 10
A stove, a stove at last!
Monday, December 3
Electricity and Flooring
We have electricity and flooring! We went with standard flooring knowing that Gigantor would likely ruin anything we put in. However we do plan to rip out the linoleum in the kitchen and tile the floor ourselves. Still no stove installed in the kitchen. Also we are missing hardware on the cabinets and fixtures in the bath tubs. Other than cleanup, I'm not sure what they are going to be doing for the next month! 

They uncovered the stairs and everything looks great!
The frameless shower...which is oddly framed at the top. huh?
Sunday, November 18
Insta-Lawn
Tuesday, November 13
Delayed!!
We found out over the weekend that the house is going to be 3 weeks late!! Bohoo. All you neigh sayers were right.